Schedule of investment

Bałtyk 1

up 104 turbines

Number

80 km

Distance from shore

1560 MW

Installed capacity

128,5 km2

Area

2025 year

Offshore wind auction

ŁEBA GDYNIA GDAŃSK BAŁTYK 1 BAŁTYK 2 BAŁTYK 3 USTKA STACJA KRZEMIENICA LĘDOWO
2012

Permit

Location permit

2019

CONNECTION CONDITIONS

Connection conditions statement from the transmission system operator

2021

AGREEMENT

Agreement for connection to the transmission network of the National Electricity System

2020-2022

MARINE ENVIRONMENTAL STUDY CAMPAIGN

Comprehensive program of marine environment study

©MEWO
2022-2023

ONSHORE ENVIRONMENTAL STUDIES

Environmental studies

WIND MEASUREMENT CAMPAIGN

Wind measurement campaign

©MEWO
2024

DECISION planned

Environmental decision for the offshore wind farm

2025

DECISION planned

Environmental decision for the connection infrastructure

AUCTION planned

Offshore wind auction

Bałtyk 2

50 turbines

Number

37 km

Distance from shore

720 MW

Installed capacity

122 km2

Area

2027 year

Planned commissioning

ŁEBA GDYNIA GDAŃSK BAŁTYK 1 BAŁTYK 2 BAŁTYK 3 STACJA WIERZBIĘCINO USTKA LĘDOWO
2012-2014

MARINE ENVIRONMENTAL STUDY CAMPAIGN

Comprehensive program of marine environment study

2013

PERMIT

Location permit

2017

DECISION

Environmental decision for the offshore wind farm

2017-2019

DECISION

Wind measurement campaign

©MEWO
2019

CONNECTION CONDITIONS

Connection conditions statement from the transmission system operator

2020

EXAMINATION

Examining seabed for UXO (presence of unexploded ordnance) and chemical weapons

©Equinor&Polenergia
2021

AGREEMENT

Agreement for connection to the transmission network of the National Electricity System

SUPPORT MECHANISM

Right to cover negative balance of the generated electricity

2021-2022

ONSHORE ENVIRONMENTAL STUDIES

Environmental studies

2022-2023

STUDIES

Geotechnical studies on land and geotechnical campaign at sea; Seabed examination

©MEWO
2023

DECISION

Environmental decision for the connection infrastructure

2024

PERMIT

Building permits

2027

COMMISSIONING planned

Planned commissioning

2028

COMMERCIAL PHASE planned

Handing over the investment to the commercial operation phase

Bałtyk 3

50 turbines

Number

22 km

Distance from shore

720 MW

Installed capacity

119,52 km2

Area

2027 year

Planned commissioning

ŁEBA GDYNIA GDAŃSK BAŁTYK 1 BAŁTYK 2 BAŁTYK 3 STACJA WIERZBIĘCINO USTKA LĘDOWO
2012

PERMIT

Location permit

CONNECTION CONDITIONS

Connection conditions statement from the transmission system operator

2012-2014

MARINE ENVIRONMENTAL STUDY CAMPAIGN

Comprehensive program of marine environment study

2014

AGREEMENT

Agreement for connection to the transmission network of the National Electricity System

2016

DECISION

Environmental decision for the offshore wind farm

2017-2019

CAMPAIGN

Wind measurement campaign

©MEWO
2020

EXAMINATION

Examining seabed for UXO (presence of unexploded ordnance) and chemical weapons

2021

SUPPORT MECHANISM

Right to cover negative balance of the generated electricity

2021-2022

STUDIES

Onshore environmental studies

2022-2023

STUDIES

Geotechnical studies on land

CAMPAIGN

Geotechnical campaign at sea; Seabed examinations

2023

DECISION

Environmental decision for the connection infrastructure

2024

PERMIT

Building permits

2027

COMMISSIONING planned

Planned commissioning

2028

COMMERCIAL PHASE planned

Handing over the investment to the commercial operation phase