Purchase calendar for Bałtyk 2 and Bałtyk 3
Name of selected supplier
Date of supplier selection
| Procurement package | Tier 1 supplier | |||
|---|---|---|---|---|
| design | prefabrication | transport & instalation | installation unit | |
| Wind turbines |
Siemens-Gamesa
|
Siemens-Gamesa
|
Siemens-Gamesa
|
Cadeler
|
| Foundations |
Ramboll
Ramboll
|
Sif Group
Smulders/Sif
|
Heerema
|
Heerema
|
| Inter-array cables |
Seaway7
|
Seaway7
|
Seaway7
|
Seaway7
|
| Export cables |
Jan De Nul + Hellenic Cables
|
Jan De Nul + Hellenic Cables
|
Jan De Nul + Hellenic Cables
|
Jan De Nul + Hellenic Cables
|
| Electric system infrastructure |
Hitachi Energy
|
Hitachi Energy
|
Hitachi Energy
|
|
| Offshore Substations |
Ramboll
Iemants (Smulders)
|
Iemants (Smulders)
|
Heerema
|
Heerema
|
| Onshore cables |
Enprom
Tele-Fonika Kable
|
Tele-Fonika Kable
Enprom
|
Enprom
|
|
| Landfall |
Janicki
VSH
|
|
||
Status as of 09.2024
News & Events
All News
Offshore windfarm construction underway. Equinor and Polenergia invite residents to an information meeting in Ustka
26 May 2026
All News
Kick-off of offshore installation: the first foundations installed at Bałtyk 2 & 3
25 May 2026
All News
The Bałtyk 2 and Bałtyk 3 offshore wind farms are growing fast both onshore and offshore
30 Apr 2026